Graphical Road Work Chainage
Graphical Road Work Chainage JSP shows work progress of each defined stages for each chainage.
- Following is the demo example shown , were chainage is defined in center and its corresponding LHS and RHS is shown along with stages of them.
- Work Progress can be defined in either of 3 stages ie , Yet to Start, In Progress , Completed. There is color defined to each stage as shown below.
- We can update progress of each stage by selecting status from dropdown.
- Also we can add new chainage/row by clicking on circle shown in bottom right of screen.
- We Can defined stages as per requirement and it can be added in ERP ADMIN > GRAPHICAL REPORT MASTER FORM.