Overdue Activities :-  It mean Activities DPR  quantity is  0 and Current date is greater than Activities  End dates

Activity Not Started. :-  It mean Activities DPR  quantity is  0 and Current date in between  Activities start amd End date 

Activity Not Completed :- It mean Activities DPR  quantity is  Not consume 100% and Current date in between  Activities  start amd End date 